This project has been recommended for LABC Built in Quality Awards. Conversion of 4 barns into
exclusive residential units for the Duchy of Lancaster Estate. Consisting of the demolition of several buildings, controlled removal of asbestos, complete strip out throughout, installation of steel beams to support roof structures, alterations to masonry walls, complete re-roofs, excavations of internal floors, underpinning, chemical injection damp proof course, installation of first floor, installation of insulation to roof and newly formed internal skin to walls.
New drainage including water treatment plants and rain water recycling systems, plumbing & under floor heating through out, electrical and alarm installation, dry lining and plastering, first and second fix Joinery including new hardwood doors and windows. Complete re-pointing of external brickwork, landscaping including paving and tarmac parking area fencing and soft landscaping.
This project was programmed to be completed within 63 weeks; completion was ahead of schedule and to budget.